|
2001 Future Energy Challenge
Specification Expectation
Inverter Specifications
The inverter project results will be judged against a set of objective specifications while achieving the example design targets shown below.
The design concept should target a 10 kW system, while teams are asked to construct a 1.5 kW prototype to demonstrate their
accomplishments. The target design requirements for the 10 kW system given below are minimums that need to be reached to win the
Challenge Award of $50,000. Scoring will be set up such that
improvements beyond the minimums are beneficial to the team. More detail will be published in the official 2001 Future Energy
Challenge Rules.
| Design Concept/Function, 10 kW System |
Minimum Target Requirement |
|
| 1. Manufacturing cost |
No more than $500 when scaled to a 10 kW
design in high-volume production. |
|
| 2. Complete package size |
A convenient shape with volume less than 50
L. |
|
| 3. Complete package weight |
Mass less than 32 kg for a 10 kW unit, not
including energy sources or batteries. |
|
| 4. Output power capability |
10 kW continuous.
Single-phase split 120V/240 V, 60 Hz output
suitable for domestic applications. Each of the split outputs should
provide 0 to 5 kW continuous, with the total not to exceed 10 kW. Output
current rating should support up to 10 kVA total loading
continuously. |
|
| 5. Input source |
48 V dc nominal source (tolerance range 42
V to 72 V) with slow transient
characteristics. See the source transient
behavior given in the Test Considerations
section below. |
|
| 6. Overall energy efficiency |
Higher than 90% for 10 kW resistive load. |
|
| 7. Total harmonic distortion |
Output voltage THD: less than 5% when
supplying a standard nonlinear test load. |
|
| 8. Safety |
The system is intended for safe, routine use
in a home or small business by non-technical
customers. |
|
| 9. Voltage regulation |
Output voltage tolerance no wider than
±6% over the full allowed line voltage and
temperature range, from no-load to full-load. Frequency 60±0.1 Hz. |
|
| 10. Acoustic noise |
No louder than conventional domestic
refrigerator. Less than 50 dBA sound level
measured 1.5 m from the unit. |
|
| 11. Electrical noise |
Able to meet FCC Class A--industrial
requirements for conducted and radiated
EMI. |
|
| 12. Protection |
Self-protection against output short
circuit, over current, over temperature,
over voltage, and under voltage or loss of
input source with no damage caused by any
of these. |
|
| 13. Environment |
Suitable for indoor installation
in domestic applications, 10°C to 40°C possible ambient range. |
|
| 14. Lifetime |
The system should function for at least ten
years with routine maintenance when
subjected to normal use in a 20°C to 30°C
ambient environment. |
|
| 15. Technical report |
Design, simulation, experiment results,
lifetime analysis, and cost study. |
|
Hardware Prototype
To confirm the design concept, function, and the benefits of any new innovations, teams are expected to construct a working prototype
scale system. The prototype nominal power level of 1.5 kW has been selected to facilitate both the student team design process and the
final competition evaluation process. Prototypes should be fully functional, to meet the specifications given below. Late in Spring
2001, submitted reports and other materials will be evaluated by the judges. A small group of teams will be selected as Finalists, and
supported to travel to a Final Competition at a national test site. At the site, prototypes will be tested against the specifications to
help validate the system design and the team's concepts.
| Prototype Specifications, 1.5 kW Scale
System |
|
|
| 1. Output power rating |
1.5 kW continuous. |
|
| 2. Phase(s) |
Split single-phase, each output rated for 0 to
750 W, not to exceed 1500 VA total. |
|
| 3. Output voltage |
120 V/240 V nominal. Frequency: 60 Hz ± 0.1
Hz. Standard outlets for loads: two NEMA type 5-15R receptacles for 120 V
loads and one NEMA type 6-15R receptacle for 240 V loads.. |
|
| 4. Battery power |
Team may elect to use a lead-acid battery
or set, with total nominal rating below 500
W-hr, for control power or as a temporary
source. If this is used, charging and charge
management must be provided, such that
charge is unchanged at the end of a 24-hr
test sequence. ("Nominal" refers to the product of nominal volts
and amp-hours based on a 10-hour or 20-hour discharge.) |
|
| 5. Safety |
The final rules will contain detailed safety
information. No live electrical elements
are to be exposed when the unit is fully
configured. |
|
| 6. Grid and source interaction |
The inverter is intended as a stand-alone
unit for remote power or backup power. No
power (or current) backfeed to the source is
permitted. |
|
| 7. Inrush and current limits |
Maximum current drawn from the fuel cell shall not exceed 55 A under any
circumstances, except that a peak short-term current pulse drawn from the input source
at start-up or connection shall not exceed 100
A. Duration of this short-term pulse shall not exceed 5 ms. |
|
| 8. Storage temperature range |
0 to 60°C |
|
| 9. Operating ambient temperature range |
10 to 40°C |
|
| 10. Other ambient |
Intended for indoor applications,
non-condensing humidity environment, but must be
spillproof. |
|
| 11. Shipping environment |
Can be shipped by conventional air freight
or truck freight. |
|
| 12. Protection |
Over current, over voltage, short circuit,
over temperature, and under voltage. No
damage caused by output short circuit. The
inverter must shut down if the input voltage
dips below the minimum input of 42 V. Inverter should not self-reset after
a load-side fault. IEEE Std. 929
is a useful reference. |
|
| 13. Design input source type |
Fuel cell, photovoltaic, microturbine or
other qualified renewable energy sources.
Prototype tests will use a fuel cell system
with a nominal rating of 48 V dc, as listed below, and a power supply configured
for 48 V dc output. |
|
| 14. Electromagnetic interference |
Per FCC 18 Class A -- industrial (not subject
to test) |
|
| 15. Communication interface |
RS232 or USB standard computer interface.
Standard commercial software to be
provided by the team to the test lab for
acquiring any inverter internal data and
recording it via a conventional spreadsheet. (Provision for internal data
is optional, but a standard interface is to be provided if internal data
acquisition is present.) |
|
| Prototype Test Considerations |
|
|
| 1. Inspections |
All prototypes of approved Finalist teams
must pass safety inspection prior to
operation. All prototypes must function
correctly during a 15-minute initial
operation check with a power supply input before proceeding to fuel-cell tests. |
|
| 2. Test energy source: voltage |
Prototypes will be tested with a fuel cell
source, 48 V nominal (42 V to 72 V range).
Nominal power: 1.5 kW continuous measured at inverter output. |
|
| 3. Test energy source: power |
1.5 kW or less, continuous output referenced to
inverter output (actual source power will provide up to 1.8 kW to account for
inverter losses). |
|
| 4. Test energy source: transients |
Initial Startup: 90 s to initial steady state.
Short term (unadjusted fuel cell inputs): 10
s to new steady state.
Long term (adjusted fuel cell inputs): 60 s to
new steady state (from idle and above). |
|
| 5. Input current
transients (ripple). (Note that these limits match those from the NETL
PowerPoint presentation from the March meeting in Anaheim.) |
Peak-to-peak current ripple measured from the fuel cell, relative to the
average current, over the inverter output load range
- 120 Hz ripple: < 15% from 10% to 100% load, not to exceed
0.6 A for lighter loads.
- 60 Hz ripple: < 10% from 10% to 100% load, not to exceed
0.4 A for lighter loads.
- 10 kHz and above: < 60% from 10% to 100% load, not to exceed 2.4 A for lighter
loads
- >120 Hz to <10 kHz, limit linearly interpolated between the 120 Hz and
10 kHz limits.
- Teams will benefit in scoring for lower ripple levels. Maximum
points will be received for ripple levels a factor of ten
below the above maximum limits
- Transients below 60 Hz represent "load following" action of the
system, and should track the Maximum Available Current signal from the fuel cell to
within 1% for purposes of both fuel cell integrity and efficiency.
|
|
| 6. Test energy source: control interface,
signals from energy source to inverter |
a) Fuel Cell Trip -- Digital TTL level,
high=Fuel Cell Operable/Ready, low=Fuel
Cell Trip/Not Ready.
b) Available Power Level -- Analog 0-5 V
signal representing the maximum power available from the source at a given
moment.
|
|
| 7. Test energy source: control interface,
signals from inverter to energy source |
a) Inverter On/Off -- Digital TTL level,
high=On, low=Off. Tells fuel cell to start
up or to shut down. b) Power Level Control -- Analog
0-5 V
signal to request a power level from
minimum (idle) to maximum. Tentative gain setting is 1.8 kW full scale
(360 W/V). |
|
| 8. Test duration |
Operation will be tested for up to 24 hr
continuous, total. The test sequence will include load tests with fuel
cell input and performance tests with a power supply input arranged to
simulate a fuel cell. The test sequence will be specified in a separate
spreadsheet. |
|
| 9. Test loads |
Linear load: Resistive load and inductive
load with 0.8 power factor. Nonlinear load:
rectifier load similar to computer power supplies, specified here.
An additional test load with dynamic
characteristics will be used to model a 24
hr domestic load cycle. Circuit models for
test loads will be provided. |
|
| 10. Typical operation tests |
Tests for steady-state performance (including
regulation and harmonic distortion),
protection, robustness to external faults,
acoustic noise. Test methods will conform to IEEE Standard 1515. |
|
| 11. Source interface tests |
Tests for transient loads and interaction
with the input fuel cell. Load ramp rates
will be examined to determine suitability
for the fuel cell application. |
|
Specification Intent
The specifications are intended to provide guidance rather than an exhaustive list of requirements. All teams are encouraged to
develop novel solutions and test a wide range of ideas. The long-term purpose is to develop cost-effective technologies that will bring
alternative energy to homes and businesses. Judges will be encouraged to consider the spirit, innovation, and future promise of each
team's work when reviewing entries.
Design Restrictions
In general, any electrical, electronic, energy, mechanical, or other component may be used in the 10 kW system design. Keep in mind the
cost considerations and the intended safe use in domestic applications. Both factors will limit the feasible range of component choices.
Awards
The $50,000 Challenge Award, provided by the
U.S. Department of Energy, is given for highest score among entries meeting all minimum requirements for the 10 kW system design, as confirmed through reports
and prototype tests. Program Awards, provided by the U.S. Department of
Defense, in the amount of up to $5,000 each, with a total of $25,000 to be
awarded, will be given for the best results in specific topic areas (such as
best thermal design, packaging, prototype quality, reports, and
others).
Period of Competition and Key Dates
September 1, 2000 to August 31, 2001, with an
Awards Banquet to be held in September or October 2001.
Project report due date: June 15,
2001. Test sequence dates: the week of August 13, 2001.
Judging Panels and Judging
Experts from IEEE Power Electronics Society, Industry Applications Society, Industrial Electronics Society (and others to be
announced), and representatives from manufacturers, national labs, independent test labs, utilities, and R&D engineers.
Student team project results will be judged based on cost effectiveness, performance, quality of the prototype and other results,
engineering reports, adherence to rules and deadlines, innovation, future promise, and related criteria. Each aspect of judging will be
scored according to a point list and Test Protocol published in the 2001 Future Energy Challenge Rules.
Judging involves four primary steps:
- Judging of the Project Reports. The
judges will be asked to score the Project Reports based on quality of the
design, quality of the results, and quality of the report. The judging
results will be used to identify up to five Finalist Teams that will be
invited to participate in tests at the National Energy Technology
Laboratory, Morgantown, West Virginia.
- Quantitative Scoring. Each Finalist
team will receive a point score based on actual test results.
- Qualitative Scoring. Each Finalist team
will be evaluated based on a presentation at the test site, based on quality
of documentation and prototype, and based on other aspects of the rules and
specifications.
- The two or three teams with the designs
judged to have the lowest cost will have their designs forwarded to one of
our industrial partners for a detailed costing analysis. The Challenge
Award recipient must achieve the $500 cost target based on this analysis.
Project Report
Each team is expected to submit a formal
engineering report that describes the design, simulation and test results,
project activities, and prototype performance. This Project Report should
be written to address three key objectives:
- Present the team's 10 kW inverter design and
report on the actual project activities.
- Demonstrate that the design will meet the
specifications and requirements.
- Demonstrate operational success with the
prototype hardware sufficient to qualify the team as a Finalist in the
evaluation of the judges.
Only those teams with functioning prototypes will qualify as Finalists, so
thorough demonstration of actual test results from prototype hardware should be
an important element of the Project Report. Teams that are not able to
develop fully functional hardware will still be eligible for Program Awards
based on the Project Report.
Report Format and Content Requirements
Project reports should not exceed 50 pages, double-spaced on 8 1/2" x
11" paper. The main font size should not be smaller than 11
point. The original copy of the report should be signed by the team's
faculty advisor and the authors of the report. A title page, signature
page, table of contents, abstract, and list of references should be included but
are not counted as part of the 50-page limit.
Project reports should include, at a minimum:
- Design rationale and feature description.
- Basic performance evaluation (through simulation and other means).
- Cost evaluation based on the spreadsheet developed by the Organizing
Committee.
- Analysis of theoretical and experimental results.
- A discussion of project management, the team's organization and operation,
and the educational impact of the project.
In addition to the primary 50-page report, an Appendix should be provided
that includes:
- Detailed schematics and unusual material-safety data sheets.
- Operating instructions for the prototype hardware. (A final version
of the operating instructions are to be shipped to Morgantown with the
Finalist prototypes.)
Teams are encouraged to include certain additional items in the Appendix:
- Biographical material about team members.
- Documentation about special course offerings that were associated with the
project.
- Copies of publicity materials that the team would like to share with
organizers.
Other information that the team believes will validate the design and help
the judges qualify the team as a Finalist should be provided in the 50-page
report based on the best judgment
of team members and faculty advisors. The report is not intended to serve
as a "User Manual" for the inverter design or for the prototype, but
it should include enough operating detail to permit an experienced technician to
connect and test the prototype. However, if a team wishes to prepare a
user manual, this is encouraged. It should be provided as a separate
document, and will not be considered part of the report judging process.
Due Date
The Project Report must be received at the address below by close of business on
June 15, 2001 for full consideration. Project reports sent to Los Angeles will
be assembled and forwarded to Vancouver for
processing. Ten bound copies and one unbound copy of the
report must be sent to:
Robert Myers
Phone: (310) 446-8280
Administrative Secretary
Fax: (310) 446-8390
IEEE Power Electronics Society
E-mail: bob.myers@ieee.org
799 North Beverly Glen
Los Angeles, CA 90077
Alternatively, the Project Report will still receive full consideration
if the
required copies are received by the close of business on June 18, 2001 at
Robert Myers, Future Energy Challenge
c/o Prof. William Dunford
Dept. of Elec.
Eng.
University of British Columbia
2356 Main Mall
Vancouver V6T 1Z4
CANADA
Phone: (604) 822-6660
For teams with members who will be attending the IEEE Power Electronics
Specialists Conference in Vancouver, British Columbia, it is acceptable
to deliver the report copies in person to Robert Myers at the
registration desk by the close of business on Monday, June 18, 2001.
|