The
International
2003
Future Energy Challenge
A
student competition sponsored by the
Institute of Electrical and
Electronics Engineers (IEEE) - Power Electronics Society, Industry Applications Society, and Power
Engineering Society
by the U.S. Department of
Energy and the U.S. Department of Defense
and other sponsors
Additional
specification elements added or edited after July 15, 2002.




Summary of changes after July 15, 2002 (no changes were made between May 2 and
July 15, 2002):
Topic (c) is no longer active
because of limited proposal submissions.
A version of this topic will be present in the 2005 FEC.
Firmer dates have been listed for
the final competition events and the February workshop.
Clarification to output
requirements for topic (a) has been provided.
Additional clarification to
output requirements for topic (a) added, November 2002.
Summary of
changes, April 15 through final posting on May 2:
Topic (c) included in detail.
Topic (a) minor revisions to the
target mass (increased to 30 kg) and to provide a consistent volume limit (88.5
L). The minimum efficiency is now 90%,
although scoring will be arranged so that there are extra benefits to achieving
the prior target of 94%.
Clarifications added in certain
places such as the output power specification for topic (a) and the input power
sources for topic (c).
Two sponsors (FTC and the
Grainger Center) have been added.
Teams should plan to submit an
electronic version (PDF format) of their proposal with the printed copies. Electronic versions will help to expedite
the review process.
Summary of Competition and Proposal
Requirements
General Information
Competition Title: 2003 International Future Energy
Challenge student Competition
Topic areas: (a) Fuel cell energy
conversion, (b) Single-phase adjustable-speed motors, and (c) Low-cost power
for developing nations.
Period of Competition: August 1, 2002
to July 31, 2003
Challenge Award
At least
US$10,000 (and up to US$50,000, based on sponsorship) will be awarded for
highest score among entries meeting all minimum requirements, as confirmed
through reports and hardware tests.
Program Awards (actual number depends on availability)
Best in specific
topic areas (engineering design, reports, and others): expected levels are $3,000 to $5,000
each. The final amounts are subject to
the recommendations of the judges.
Intellectual Property and Use of Prize Money
The Future
Energy Challenge does not restrict the use or protection of inventions or other
intellectual property produced by participating teams. There are no special licenses or rights
required by the sponsors. However, the
Final Test Events that begin May 19, 2003 will include public disclosure of
each team’s technology. Teams
interested in securing protection for their inventions should be aware of this
date when making arrangements.
The prizes
provided to schools are intended to benefit the team members and student team
design project activities. There is a
Letter of Support required for submission with the proposal, and it should
outline the plans of the school in the event that a prize is received.
Outside Support
Individual
schools should solicit project funding from NASEO, utilities, manufacturers,
government agencies, or other sources.
There is no limitation for the sources of project funding.
Eligibility Information:
To confirm eligibility, potential participating schools must submit a Letter of Support together with a Preliminary Team Information Form when they submit the proposal.
How to Participate: Participation is on a proposal basis. Those schools that have submitted a Letter of Intent must submit a proposal no later than May 31, 2002. Proposals will be judged by a distinguished panel of volunteer experts from the IEEE and from industry. Schools with successful proposals will be notified by August 1, 2002. Student teams will then carry out the work and prepare hardware prototypes and reports. Preliminary reports are due March 15, 2003. The reports will be judged by a similar expert panel. The panel will select a small group of teams as Finalists. These teams will be invited to a competition event that will begin May 18, 2003. A Final Report will be due at the competition event. The team achieving the best overall results that meet all the requirements will receive a Challenge Award of no less than US$10,000 (and up to US$50,000 based on sponsorship levels). The best results in individual categories, including engineering design, engineering report quality, innovation, and other categories to be determined, will win special monetary prizes of approximately $3,000 to $5,000 each.
Please be aware that each of the three topic areas
of the 2003 Future Energy Challenge will be judged separately, against a
separate specification set. Each team
proposal must address a single topic area.
Judging Panels
Experts from
IEEE Power Electronics Society, Industry Applications Society, Power
Engineering Society(and others to be announced), and representatives from
manufacturers, national labs, independent test labs, utilities, and R&D
engineers.
Judging
Student team
project results will be judged based on cost effectiveness, performance,
quality of the prototype and other results, engineering reports, adherence to
rules and deadlines, innovation, future promise, and related criteria. Each aspect of judging will be scored
according to a point list and Test Protocol published in the 2003 Future Energy
Challenge Rules.
Proposals
Proposals will
be judged on the quality of plans, the likelihood that a team will be
successful in meeting the Future Energy Challenge objectives, technical and
production feasibility and degree of innovation. Other key criteria are evidence of the school's commitment,
capability, experience, and resources to implement their design over the
one-year span of the competition. Commitment to excellence in undergraduate
education is important, and acceptable proposals will involve undergraduate
students as the primary team members. Interdisciplinary teams are encouraged. Graduate students are not
excluded, but the impact on undergraduate education is a critical judging
criterion. Proposals are limited to 12
double-spaced pages total, including all diagrams, attachments, and
appendixes. Schools that are invited to
participate in 2003 Future Energy Challenge are expected to adhere to the basic
plans described in their proposals.
Approval of the competition organizers must be sought for significant
changes in plans or engineering designs.
Only one proposal per topic will be considered for any school, but each
topic requires a separate proposal and team.
Eleven copies of the proposals are due, to be received by May 31,
2002, at the mailing address provided below.
A. Proposal
Objectives
Respondents
should express their ideas and plans relevant to their interested topic
area. The project should include the
construction and operation of a complete hardware prototype. The proposal must address both technical and
organizational issues for each phase of the prototype’s development and
testing. It must contain a realistic
project budget, along with a plan to secure the necessary funding. The educational goals, including any course
credit provided for work related to 2003 Future Energy Challenge, and how the
project relates to other efforts within the school and at the regional or
national level should be addressed. A
Letter of Support from an official of the school confirming a commitment to
participate in the competition, and stating the type(s) and level of support
for the team's participation in the competition should be attached, and is not
counted toward the 12-page limit. Refer
to the attachments at the end of this document for a sample.
B. Administrative
Considerations and Limitations
This section describes the
limitations placed on the proposal.
Compliance is mandatory.
Language Proposals must be written in English.
Length
Proposals are
limited to 12 single-sided double-spaced pages of text, figures, and
appendixes. The page size must be
8.5" x 11" or A4 and the font size must be no smaller than 10
point. Margins should be at least 25
mm. The Preliminary Team Information
form (Attachment 1 in this RFP), support letters from the school, government
entities, or private sector organizations will not count in the proposal
length.
Authors Proposals are to be prepared by
the student team in collaboration with the faculty advisors.
Signatures Proposals must be signed by all authors
of the proposal and the faculty advisor.
Letter
of Support Proposals must
be accompanied by a letter of support from an appropriate Dean, Department
Chair, or other authorized school official.
The letter must confirm the school’s commitment to participate. It must also state the type(s) and value of
support from the institution. School
support should match the value of cash and in-kind support from the team's
principal sponsors. Additional letters
of support from other team sponsors are optional. A sample is provided as Attachment 2.
Preliminary
Team Data Submit one copy
of the Preliminary Team Information form (Attachment 1) with the proposal, then
an updated copy with the preliminary report to the address below. This form does not count in the 12 page
limit.
Due
Date All proposals must
be received at the address below by close of business on May 31, 2002
for full consideration.
Number
of Copies Ten bound copies
and one unbound copy of the proposal must be sent to:
Administrative
Secretary Fax: (310)
446-8390
IEEE Power
Electronics Society E-mail: bob.myers@ieee.org
IEEE
Industry Applications Society
Los Angeles, CA 90077
We would also prefer to have an
electronic copy, in PDF format, delivered on floppy disk (IBM format) or CD
with the proposal copies.
For Information
Non-technical or
administrative questions should be directed to Mr. Robert Myers, bob.myers@ieee.org. Technical questions should be directed to
the Future Energy Challenge Organizing Committee. The Chair is Prof. Jo Howze, Texas A&M University,
howze@ee.tamu.edu. The Vice-Chair is
Prof. Fang Peng, Michigan State University, fzpeng@egr.msu.edu. The competition website is http://www.energychallenge.org;
this final version of this RFP will be posted on the website.
Time Schedule
April 8,
2002 - schools submit letter of
intent
April 15,
2002 - Request for Proposals (RFP) sent
(electronically) to schools that provide a Letter of Intent
April 15-30,
2002 – RFP is available for comments and questions from potential teams, and
subject to editing in response to comments.
(Final official RFP posted May 2, 2002.)
May 31,
2002 - proposals due
August 1,
2002 - schools informed of
acceptance into competition
February 9-13,
2003 - Future Energy Challenge
Workshop will be held during the IEEE Applied Power Electronics Conference,
Miami Beach, Florida, USA. See
http://www.apec-conf.org for conference information
March 15,
2003 - preliminary reports due
April 15,
2003 - finalists notified
May 18, 2003 –
final competition: reception in
Morgantown, WV for topic (a) participants
May 19-22, 2003
– final competition events for topic (a).
Final reports due.
May 21-24, 2003
– final competition events for topic (b).
Final reports due.
July, 2003 - awards ceremony at 2003 PES general meeting
Competition
Description
Scope: An international student competition for innovation,
conservation, and effective use of electrical energy. The competition is open to college and university student teams
from recognized engineering programs in any location. Participation is on a proposal basis.
Introduction: In 2001, the U.S. Department of Energy
(DOE), in partnership with the National Association of State Energy Officials
(NASEO), the Institute of Electrical and Electronics Engineers (IEEE), the
Department of Defense (DOD) and other sponsors, organized the first Future
Energy Challenge competition. The
objective was to build prototype, low-cost inverters to support fuel cell power
systems. This competition was
originally open to schools in North America with accredited engineering
programs. The 2001 Future Energy
Challenge focused on the emerging field of distributed electricity generation
systems, seeking to dramatically improve the design and reduce the cost of
dc-ac inverters and interface systems for use in distributed generation
systems. The objectives were to design
elegant, manufacturable systems that would reduce the costs of commercial
interface systems by at least 50% and, thereby, accelerate the deployment of
distributed generation systems in homes and buildings. The 2001 Challenge was a success, and is now
the first in a biannual series of energy-based student team design
competitions.
To continue and
expand the 2001 success, the 2003 Future Energy Challenge has been organized as
a worldwide student competition. The
theme of the 2003 Future Energy Challenge is "Energy Challenge in the
Home." The objective is to
introduce engineering design innovations that can demonstrate dramatic
reductions in residential electricity consumption from utility sources or that
can lead to the best use of electricity in newly connected homes in developing
nations. The innovations should be low
in cost, and should have broad potential for the future.
Topics and
Descriptions: The
competition addresses three broad topic areas: (a) fuel cell energy conversion,
(b) single-phase adjustable-speed motors, and (c) low-cost power for developing
nations, respectively described as follows:
a)
Energy
processing to support the use of solid-oxide fuel cells to provide non-utility
and ultra-clean residential electricity.
The US Department of Energy and Department of Defense have agreed to
provide prize money for substantial cost reductions in inverter technology for
such sources. The target cost is less
than US$40/kW for a 10 kW inverter interface system (not including an electric
grid interface nor the battery). The
hardware prototypes judged as best will be tested in a fuel cell system at the
DOE National Energy Technology Laboratory. The school with the most
cost-effective design and that can meet or exceed the aggressive cost target,
and that provides a fully functional prototype, will be awarded with a large
prize.
b)
Innovations
in motors and motor drive systems that produce deep cuts in losses and costs
for home (appliance) use, or that could replace “universal motor” brush
machines in residential applications.
For example, use three-phase motors and motor drives that operate from
single-phase power, reduce appliance in-rush currents associated with motor
starting, and enhance motor efficiency across a wide load range are of
interest. Target hardware costs are
US$40 for a combination motor and motor controller that can operate from a
single-phase residential source, deliver rated shaft load of 3/4 HP (or 500 W)
at 1500 RPM, exhibit a useful speed control range of at least 150 RPM to 5000
RPM, and provide power efficiency of at least 70% for loads ranging from 50 W
to 500 W at a specified speed. The hardware prototypes judged as best will be
tested at a DOE or DOD National Laboratory. The school with the most
cost-effective design and that can meet or exceed the aggressive cost target, and
that provides a fully functional prototype, will be awarded with a large prize.
c)
Efficient,
cost-effective electrification for homes in developing nations. This involves low-cost local energy sources,
and emphasizes innovations to allow small amounts of power to make significant
impacts on standards of living. The
target system addresses ways to produce and use a power-limited 100 W
source. The objectives are to prepare a
cost-effective low energy source, and to improve the quality of life in the
most effective manner for a household if just a small power level is
available. The system involves the
design of small, low-cost, self-contained solar, wind, or other non-fuel power
systems (plus any energy storage), capable of delivering 100 W over several hours
at costs in the range of US$0.10/kWhr to US$0.20/kWhr when amortized over a
required ten-year life. The system
should provide for prioritized control of three different domestic loads. Entries and prototypes will be judged with
the assistance of the Construction Engineering Research Laboratory, U.S.
Department of Defense, or through arrangements with government or scientific
facilities in other nations.
Detailed
Description, Proposal Preparation and Specifications of Each Topic
Request for
Proposals – Topic (a) Fuel cell energy conversion
The main goal of the Fuel Cell Inverter Challenge is to develop low-cost power processing systems that support the commercialization of a solid-oxide fuel cell (SOFC) power generation system to provide non-utility and ultra-clean residential electricity. For residential applications, the 5 kW SOFC is supplemented with a 5 kW battery set to meet extended-duration power-demand periods exceeding 5 kW and short-duration transient high power loads. Thus the target inverter rating is 10 kW. The US Department of Energy and Department of Defense have agreed to provide prize money for substantial cost reductions in inverter technology for such sources. The competition runs under the auspices of the IEEE Power Electronics Society, the IEEE Industrial Applications Society, The IEEE Power Engineering Society and the IEEE Industrial Electronics Society.
The target cost of a stand-alone, i.e. non-utility linked, 10 kW power processing unit should be less than US$40/kW for the inverter interface system when produced at large quantities. Emphasis is also placed on high-energy efficiency as this has direct impact of size and cost of the SOFC system and overall system fuel efficiency. The hardware prototypes judged as best will be tested first in a fuel cell emulator and subsequently in a fuel cell system at the DOE National Energy Technology Laboratory. The fuel cell system will be provided by Fuel Cell Technologies, Ltd. The school with the most cost-effective design, which meets or exceeds the aggressive cost target, and provides a fully functional prototype, will be awarded with a large prize. In the event that multiple designs meet the specification requirements, and are judged to be comparable on a cost basis, the Challenge Award will be given to the design with the best energy efficiency.
Vision
Encourage the development of
technologies to reduce the cost of inverters (power processors) that are
designed for domestic
energy sources.
Incorporate practicality, potential manufacturability, and affordability into the competition assessment process.
Demonstrate technical progress
toward and potential of advanced technologies that may help achieve the goals
of this competition.
Improve engineering education and
foster practical learning through the development of innovative team-based
engineering solutions to complex technical problems.
Goals
Construct an
inverter that will:
Reduce the manufacturing cost to
less than $40/kW per unit;
Achieve maximum efficiency;
Achieve minimal size and weight
requirements;
Minimize cooling requirements;
and,
Develop a power processing system
which realizes acceptability of fuel cell energy systems in the areas of
performance (in steady state and under dynamic conditions), reliability and
safety.
The inverter
proposed will be judged against a set of objectives, requirements and
characteristics given below. The
inverter design concept should target a 10 kW (peak) residential power
generation system with 5 kW from an SOFC and 5 kW from a battery set. During overload the system draws 5 kW from fuel cell and 5 kW
from battery for max. 1 min. To cope
with the slow dynamic response of the fuel cell, the 48 V battery pack is also
used as a secondary energy source to supply transient loads. A 48 V battery pack as described in the
following minimum requirements will be provided at the competition test
site. Student teams may elect and
propose to provide this 5 kW of supplemental power by some other means. If a team elects to do so, then the team
will be responsible for providing their own supplemental 5 kW power source in
time to support testing at the competition test site. The fuel cell needs auxiliary power to run
its internal circuits, such as balance-of-plant and control sub-systems. This load is 1 kW and has to be managed by
the inverter as well. The target design requirements for the 10 kW system given below
are minimums that need to be reached to win the Challenge Award of $50,000.
Design concepts must be validated with working prototypes. Scoring will be set up such that
improvements beyond the minimums are beneficial to the team, with
significant weight on energy efficiency. More detail will be published in the
official 2003 Future Energy Challenge Rules.
|
Design Item |
Minimum
Target Requirement 10 kW System |
|
|
1. Manufacturing cost |
Less than US$40/kW for the 10 kW design in high-volume
production. |
|
|
2. Complete package size |
A convenient shape with volume less than 88.5 dm3 (88.5 L). |
|
|
3. Complete package weight |
Mass less than 30 kg, not including energy source (SOFC) or
auxiliary energy storage batteries1. |
|
|
4. Output
power capability – nominal Output power capability – overload Current limit (short circuit) |
5 kW continuous, total (5 kW continuous @ displacement factor 0.7,
leading or lagging, max. from each phase) 10 kW overload for 1 minute (half of input from fuel cell and
half from battery1 supply) @ d.f. 0.7 (lead or lag). 5 kW @ 0.7 d.f. max. from each phase. Notice that the phase maximum
requirements are the same under continuous and overload conditions. Unit shall shut down if the output current exceeds 110 % of
maximum rated value. Teams may select
either to continue supplying current or to shut down for currents >100%
and <110%. |
|
|
5. Auxiliary power feed for fuel cell control unit |
Unit
shall provide an additional NEMA 5-15R outlet to supply 120 Vac/60 Hz for the
fuel cell control unit. The load will
not exceed 1 kVA, and the displacement factor will not be less than 0.7. This outlet can be connected to either of
the output phases, or can be separate at the team’s discretion. This load is counted as part of the total
inverter output load for testing purposes. Unit
shall provide a connection to supply 48 V dc, +/- 2.5%, for the fuel cell
control unit. The load will not
exceed 300 W. This 48 V auxiliary
supply will be used in conjunction with the fuel cell, and electrically the
low side is connected to the negative terminal of the fuel cell. There is no requirement for electrical
isolation with respect to the fuel cell, provided the common connection is
supported. Total
power supplied to these additional outputs is included in the 5 kW
continuous and 10 kW overload maximum output. |
|
|
6. Phase(s) |
Split single-phase, for US domestic ac supply with standard NEMA
5-15R receptacles for loads "2 degrees for
balanced loads between phases. Please
provide at least four outlets per phase to support tests up to 5 kW per
phase. |
|
|
7. Output voltage |
120 V/240 V nominal (split-phase). |
|
|
8. Output frequency |
60 Hz ± 0.1 Hz. |
|
|
9. Output voltage harmonic quality |
Output voltage total harmonic distortion (THD): less than 5%
when supplying a standard nonlinear test load (Test Considerations to be
provided later). |
|
|
10. Output voltage regulation quality |
Output voltage tolerance no wider than ±6% over the
full allowed line voltage and temperature range, from no-load to full-load. |
|
|
11. Input source (SOFC) |
22-41 VDC, 29 VDC nominal, 275 A max. from fuel cell. |
|
|
12. Maximum input current ripple |
3% rms of rated current |
|
|
13. Battery auxiliary power1 |
48 V dc nom. +10%-20%, with nominal rating of 500
Whr. Battery can be used as a
temporary energy source (5kW peak equivalent at the output, 1 min.) as well
as for control power. Charging and
charge management must be provided, such that charge is unchanged at the end
of a 24 hour test sequence. |
|
|
14. Overall energy efficiency |
Higher than 90% for 5.0 kW resistive load with minimal
efficiency degradation up to peak power and down to minimum power. Additional scoring points will be awarded
for efficiencies higher than 90%. |
|
|
15. Protection |
Over current, over voltage, short circuit, over temperature, and
under voltage. No damage caused by
output short circuit. The inverter
must shut down if the input voltage dips below the minimum input. IEEE Std. 929 is a useful reference. |
|
|
16. Electromagnetic interference |
Per FCC 18 Class A -- industrial requirements for conducted and
radiated EMI. |
|
|
17. Safety |
The final rules will contain detailed safety information. No live electrical elements are to be
exposed when the unit is fully configured. The system is intended for safe,
routine use in a home or small business by non-technical customers. Industry
safety standards will be required, such as UL 1741-2000. |
|
|
18. Grid and source interaction |
None. The inverter is intended as a stand-alone unit for remote
power or backup power. |
|
|
19. Communication interface |
Control communication between fuel cell and inverter is through
RS232—see Table 1, below. Standard
commercial software to be provided by the team to the test lab for acquiring
any inverter internal data and recording it via a conventional spreadsheet. |
|
|
20. Environment |
Suitable for indoor or outdoor installation in domestic
applications. |
|
|
21. Storage temperature range |
-20 to 85 °C |
|
|
22. Operating ambient temperature range |
0 to 40 °C |
|
|
23. Other ambient |
Humidity less than or equal to 95% up to 25 °C Less than or equal to 75% at temp. above 25 °C up to 40 °C |
|
|
24. Enclosure type (suggested) |
NEMA 1 |
|
|
25. Cooling |
Air cooled |
|
|
26. Shipping environment |
Can be shipped by conventional air or truck freight. |
|
|
27. Acoustic noise |
No louder than conventional domestic refrigerator. Less than 50 dBA sound level measured 1.5 m
from the unit. |
|
|
28. Lifetime |
The system should function for at least sixteen years with
routine maintenance when subjected to normal use in a 20°C to 40°C ambient
environment. |
|
|
29. Technical report |
Design, simulation, experiment results, lifetime analysis, and
cost study. |
|
|
30. Auxiliary power availability |
The fuel cell system requires both the dc and ac auxiliary power
(see item 5 above) fully functional before it can begin to
operate. The power conversion system
can bring the dc and ac auxiliaries up in either order, but the fuel cell
system will not begin to work until both are powered up and available. (Notice that this will require power to be
drawn from the battery pack as the fuel cell comes up.) |
|
|
31. Control power |
The power conversion system must draw all its power from either
the fuel cell of the battery pack.
This does not preclude the use of small internal batteries for
nonvolatile memory or similar functions, but the conversion system should
meet the sixteen year lifetime without requiring change of any extra internal
source. (Notice that the battery pack
is assumed to be connected continuously when the conversion system is to be
in operation.) |
|
|
32. Galvanic isolation |
Galvanic isolation of the system is not a specific requirement,
because the fuel cell system can “float” electrically, but it is
encouraged. It is a
requirement that the common neutral point of the ac output phases be
available for external bonding to earth ground. |
|
Notes: 1. A 48 V battery pack as described in the following minimum requirements will be provided at the competition test site. Students may elect and propose to provide this 5 kW of supplemental power by some other means. If a team elects to do so, then the team will be responsible for providing their own supplemental 5 kW power source in time to support testing at the competition test site.
Please note that each unit should be equipped with at least nine NEMA 5-15R receptacles: four for each output phase and one additional for the required fuel cell support power.
Final Competition Prototype Testing
A detailed test protocol will be presented to the teams prior to the competition. The teams can expect two stages of testing. The first being a preliminary test on a DC power supply (fuel cell simulator), and if the inverter passes, then is evaluated on the SOFC fuel cell system. Prototypes should be fully functional and meet the minimum requirements. In Spring 2003, submitted reports and other materials will be evaluated by the judges. A small group of teams will be selected as Finalists, and some support for travel to a Final Competition at the National Energy Technology Laboratory in Morgantown, West Virginia may be available. At the site, prototypes will be tested against the requirements to help validate the system design and the team’s concepts. Testing will first be performed using dc power supplies, i.e. fuel cell simulator, and finally with a working SOFC prototype from Fuel Cell Technologies, Ltd. Guidance on competition prototype test considerations will be provided at a later date.
|
RS 232 |
The following signals are
required to the fuel cell controller computer via the RS 232 link: |
|
|
1) DC Fuel Cell Voltage NOTE: the Fuel Cell voltage cannot be below VFC min (Fuel Cell minimum voltage) |
||
|
2) DC Fuel Cell Current |
||
|
3) DC Battery Voltage |
||
|
4) DC Battery Current |
||
|
5) DC Link Voltage |
||
|
6) AC Voltage |
||
|
7) AC Current |
||
|
8) KVA Output Total from Inverter |
||
|
9) kW Output Real Power From Inverter |
||
|
10) Run |
||
|
11) PCU (or inverter) Fault |
||
|
12) “ Slew rate ” : - to deal with fast step load changes, energy is
initially drawn from the batteries. A configurable slew rate will be
transmitted from the Fuel Cell controls to the inverter. This rate will quantify the rate at which
the inverter transfers the load from the batteries back to the Fuel Cell (Amps / Sec). This is required because the Fuel Cell needs a period of time to
adjust the Fuel and Air Flow rates as the Fuel Cell output current
increases. NOTE: the rate of
change of Fuel Cell Output Current < slew rate. |
||
|
|
|
|
|
System Diagnostic on LEDs |
-
Run, Fault |
|
|
Operators |
- AC Line Breaker, DC Fuse Links |
|
|
Discrete TTL Control
Signal from Fuel Cell Controller |
1.
Enable Inverter (AUX
Bus comes alive and power is at output) 2.
Enable Grid Connect
Mode 3.
Enable Stand Alone
Mode 4.
Enable Battery
Charging 5.
Enable Battery
Equalize charging |
|
|
Software Protocol |
RS 232, RS 485, TBD
(Vendor Specific for prototype) |
|
Requirements Intent
The requirements
are intended to provide guidance rather than an exhaustive list of
requirements. All teams are encouraged
to develop novel solutions and test a wide range of ideas. The long-term purpose is to develop
cost-effective technologies with high-energy efficiency that will bring
alternative energy such as solid-oxide fuel cells to homes and businesses. Judges will be encouraged to consider the
spirit, innovation, and future promise of each team’s work when reviewing
entries. For designs of comparable
high-production volume cost estimates, the design with better energy efficiency
will be judged to be superior.
Design Restrictions
In general, any
electrical, electronic, energy, mechanical, or other component may be used in
the system design. Keep in mind the
cost and efficiency considerations and the intended safe use in domestic
applications. These factors will limit
the feasible range of component choices.
Fuel Cell Simulator
Fuel Cell
Technology, Ltd. will provide a fuel
cell simulator for initial test and evaluation of inverters during the
competition test period. The simulator
provides both steady-state and dynamic behavior to model a 5 kW SOFC prototype
design.
Solid-Oxide Fuel
Cell Power Generation System
Fuel Cell
Technology, Ltd. will provide a 5 kW solid-oxide fuel cell power generator for
use during the competition test period.
Funding Sources
DOE and DOD
provide the Challenge Award, publicity, and any related activities.
IEEE and other
sponsors provide Program Awards.
FTC, in
conjunction with NETL, will support the final testing events.
Individual
schools should solicit project funding from NASEO, utilities, manufacturers,
and NSF. There is no limitation for the
sources of project funding.
References
National
Electrical Code (NEC) 1999 (or NFPA 70)
MIL-STD-498A,
Software Requirements Specification (SRS) DI-IPSC-81433
UL
1741 “Static Inverters and Charge Controllers for use in Photovoltaic Power
Systems”
Information Sources
The US Dept. of
Energy Solid State Energy Conversion Alliance (SECA) program was established to encourage the development
of environmentally friendly solid-oxide fuel cell modules for use with commonly
available fossil fuels at low cost. A
cost goal of $400/kW within 10 years was set for developer of solid-oxide fuel
cell power generation systems.
Information on the SECA program and participants can be obtain at
http://www.seca.doe.gov/. Details on the requirements for the
developers under the SECA program can also be found in solicitation DE-PS26-00NT40854 at http://www.netl.doe.gov/business/solicit/index.html.
The National
Energy Technology Laboratory Strategic Center for Natural Gas provides access
to fuel cell project information and reports at Gas
Processing & End Use
Fuel Cells
Reference Shelf via http://www.netl.doe.gov/scng/enduse/fc_refshlf.html.
Fuel Cell Technology, Ltd. is
developing SOFC power generation systems with Siemens Westinghouse Power
Corporation, Stationary Fuel Cell Division.
Information on Fuel Cell Technology, Ltd .can be obtained at http://www.fct.ca/. Information on Siemens Westinghouse Power
Corporation solid oxide fuel cells can be found at http://www.siemenswestinghouse.com/en/index.cfm.
M. B. Gunes, “Investigation of a Fuel Cell Base
Total Energy System for Residential Applications”, MS Thesis, Virginia
Polytechnic Institute, VA, April 30, 2001.
This report provides an analysis of a residential proton exchange
membrane (PEM) fuel cell power generation system with supplemental battery
power.
Request for
Proposals – Topic (b) Single-phase adjustable-speed motor
Topic
Description
The information provided in the following is for the single-phase adjustable-speed motor topic. The objective is innovations in motors and motor drive systems that produce deep cuts in losses and costs for home (appliance) use, or that could replace “universal motor” brush machines in residential applications. For example, use three-phase motors and motor drives that operate from single-phase power, reduce appliance in-rush currents associated with motor starting, and enhance motor efficiency across a wide load range are of interest.
Target hardware costs are US$40 for a combination
motor and motor controller that can operate from a single-phase residential
source, deliver rated shaft load of 3/4 HP (or 500 W) at 1500 RPM, exhibit a
useful speed control range of at least 150 RPM to 5000 RPM, and provide power
efficiency of at least 70% for loads ranging from 50 W to 500 W at a specified
speed. The hardware prototypes judged as best will be tested at a DOE or DOD
National Laboratory. The school with the most cost-effective design and that
can meet or exceed the aggressive cost target, and that provides a fully
functional prototype, will be awarded with a large prize. Substantial funding for this topic is
provided by the IEEE Power Electronics Society, the IEEE Industry Applications
Society, the IEEE Power Engineering Society, and the Grainger Center for
Electric Machinery and Electromechanics at the University of Illinois. Total prize money will depend on the number
of schools engaged in this topic, and is expected to exceed US$25,000.
Vision
Encourage the development of
technologies to bring dramatic improvements to low-cost single-phase motor
systems for home use.
Incorporate practicality,
potential manufacturability, and affordability into the competition assessment
process.
Demonstrate technical progress
toward and potential of advanced technologies that may help achieve the goals
of this competition.
Improve engineering education and
foster practical learning through the development of innovative team-based
engineering solutions to complex technical problems.
Goal
Construct an adjustable speed
motor system that will:
reduce the manufacturing
cost to less than US$40 for a 500 W unit;
achieve maximum
efficiency and operating requirements; and,
maintain acceptability
in the areas of performance, reliability and safety.
The motor system
proposed will be judged against a set of objective specifications based on the
example design targets shown below. The
design concept is a 500 W motor system, and teams are asked to construct a
complete hardware prototype to demonstrate their accomplishments. The target design requirements for the
system given below are minimums that need to be reached to win the Challenge
Award. Design concepts are expected to be
validated with working prototypes.
Scoring will be set up such that improvements beyond the minimums are
beneficial to the team.
|
Design Concept/Function |
Minimum
Target Requirement |
|
|
1. Manufacturing cost |
No more than US$40 when scaled to high-volume production
(approximately 1 million units/year). |
|
|
2. Complete package size |
A convenient shape with volume less than 4 L. (Motor maximum dimensions are given
below.) |
|
|
3. Complete package weight |
Mass less than 8 kg for the complete system. |
|
|
4. Output power capability and speed range |
500 W continuous shaft output power at a nominal speed of 1500
RPM, and also at higher speeds up to 5000 RPM. Continuous output torque of at least 3.18 N-m at speeds from
150 RPM to 1500 RPM. |
|
|
5. Input source |
Single-phase source at 50 Hz or 60 Hz. Teams may select either to design for nominal 120 V at these
frequencies or for nominal 220 V at these frequencies. |
|
|
6. Overall energy efficiency |
Higher than 70% for shaft loads ranging from 50 W to 500 W. Efficiency will be tested at a nominal
speed of 1500 RPM. |
|
|
7. Power factor |
Power factor measured at the electrical input should be at least
80% when tested under a 500 W shaft load at 1500 RPM. Current waveform should conform to
requirements in IEC1000-3-2 standards. |
|
|
8. Safety |
The system is intended for safe use in a home appliance or
household HVAC system. |
|
|
9. Speed control |
Speed is to be controlled from start to the full 5000 RPM with a
linear 0-10 V analog signal, referenced to the unit case. Except for starting, no testing will be
performed below 150 RPM. |
|
|
9. Speed regulation and accuracy |
The actual operating speed should remain within ±5% of the
voltage command setting (2 V/1000 RPM) from no-load to full-load. |
|
|
10. Acoustic noise |
Low noise. Less than 50
dBA sound level measured 0.5 m from the unit. |
|
|
11. Electrical noise |
Able to meet FCC Class A—industrial requirements for conducted
and radiated EMI. |
|
|
12. Protection |
Self-protection against continuous stall conditions, over
temperature, or loss of input source with no damage caused by any of these
(up to the maximum storage temperature). |
|
|
13. Environment |
Open drip proof motor construction is acceptable. Ambient temperature -20°C to +40°C. Suitable for indoor or outdoor domestic
applications. |
|
|
14. Lifetime |
The system should function for at least ten years with no
maintenance needs when subjected to normal use in a 20°C to 30°C ambient
environment. |
|
|
15. Technical report |
Design, simulation, experiment results, lifetime analysis, and
cost study. |
|
|
Additional Hardware Specifications |
|
|
|
1. Inrush and starting current |
Operating current shall not exceed 150% of nominal full-load
current under any conditions, including power-on inrush and motor starts. |
|
|
2. Phases and motor phasing |
The input power source is single phase. There are no restrictions on the motor technology or motor phase count as
long as the system operates from single-phase power. |
|
|
3. Motor dimensions |
The motor itself must be no larger than NEMA Frame Size
#48. Radius from shaft center to
mounting points not to exceed three inches or 76.2 mm. Overall length (not including shaft
extension) not to exceed 7.75 inches or 197 mm. |
|
|
4. Coupling and mount |
Motor is to be provided with a footed or cradle mount with base
holes corresponding to NEMA Frame #48 (width spacing 108 mm or 4.25 in,
length spacing 70 mm or 2.75 in), located 76.2 mm (3 in) below the shaft
center. Motor shaft diameter is to be
0.50 in (12.7 mm), or the team can provide a suitable adapter to achieve this
diameter. The shaft should extend at
least 38 mm beyond the motor case. |
|
|
5. Safety |
The final rules will contain detailed safety information. No live electrical elements are to be
exposed when the system is fully configured. |
|
|
6. Connection |
The complete unit is to be provided with an IEC 320 input
connection, with a clear label stating the voltage requirement. |
|
|
7. Storage temperature range |
-20 to 60°C |
|
|
8. Bearings |
Any choice of bearings is acceptable, provided no lubrication or
maintenance will be needed during a ten-year normal duty operating life. |
|
|
9. Handling |
The unit must be robust enough for normal handling by a
technician with no special training. |
|
|
10. Shipping environment |
Can be shipped by conventional air freight or truck freight. |
|
|
11. Displays and data |
No displays or data capability are required, although a digital
display of running speed is encouraged.
A control dial with markings is required, as stated above. |
|
|
12. Command signal |
Access to the speed control voltage signal is to be provided
either through a conventional BNC jack or a pair of screw terminals. The input should be protected against
accidental polarity reversal. The
speed must return to zero if no signal is connected. |
|
|
13. Switch |
The unit must include an on/off switch. When the switch is off, the input power
must not exceed 1 W. |
|
|
Prototype Test Considerations |
|
|
|
1. Inspections |
All prototypes of approved Finalist teams must pass safety
inspection prior to operation. All
prototypes must function correctly during a 15-minute initial operation check
before proceeding. |
|
|
2. Test energy source:
voltage |
Prototypes will be tested with available power consistent with
the selected voltage rating. Either
50 Hz or 60 Hz may be used. |
|
|
3. Test duration |
An automated load sequencing operation will be tested for up to
24 hr continuous. |
|
|
4. Typical operation
tests |
Tests for steady-state performance, protection, robustness to
stalls, acoustic noise, electromagnetic noise may be conducted. |
|
|
5. Source interface
tests |
Tests for transient loads may be conducted, within the allowed
torque, speed, and power range. |
|
Specification Intent
The
specifications are intended to provide guidance rather than an exhaustive list
of requirements. All teams are
encouraged to develop novel solutions and test a wide range of ideas. The long-term purpose is to develop
cost-effective technologies that will bring major advances in motors for
homes. Judges will be encouraged to
consider the spirit, innovation, and future promise of each team’s work when
reviewing entries.
Design Restrictions
In general, any
electrical, electronic, energy, mechanical, or other component may be used and
any motor technology is permitted. Keep
in mind the cost considerations and the intended safe use in domestic
applications. Both factors will limit
the feasible range of component choices.
Funding Sources
IEEE and the
Grainger Center for Electric Machinery and Electromechanics at the University
of Illinois provide the Challenge Award.
IEEE and other
sponsors provide Program Awards.
Tentatively, DOD
will support the final testing events.
Individual
schools should solicit project funding from NASEO, utilities, manufacturers,
and NSF. There is no limitation for the
sources of project funding.
Request for
Proposals – Topic (c) low-cost power for developing nations
Topic
Description
Target total hardware and operating costs are US$850
for a complete energy supply system with a nominal output power of 100 W. Over ten years of use, this will represent
energy costs in the range of US$0.10 to US$0.20 per kilowatt-hour. The hardware
prototypes judged as best will be tested at a DOE or DOD National Laboratory,
or in collaboration with national facilities in countries of participating
teams. The school with the most cost-effective design and that can meet or
exceed the aggressive cost target, and that provides a fully functional
prototype, will be awarded with a large prize.
Substantial funding for this topic is provided by the IEEE Power
Electronics Society, the IEEE Industry Applications Society, and the IEEE Power
Engineering Society. Total prize money
will depend on the number of schools engaged in this topic, and is expected to
exceed US$25,000.
Vision
Encourage the development of
technologies to bring dramatic improvements to alternative energy systems for
homes in the developing world.
Incorporate practicality,
potential manufacturability, and affordability into the competition assessment
process.
Address
lifestyle impacts of electrification at modest power levels, and focus on those
loads most likely to improve quality of life.
Demonstrate technical progress
toward and potential of advanced technologies that may help achieve the goals
of this competition.
Improve engineering education and
foster practical learning through the development of innovative team-based engineering
solutions to complex technical problems.
Goal
Construct an energy supply system
that will:
reduce the manufacturing
and operating costs of alternative energy systems into the range of US$0.10 to
US$0.20 per kilowatt-hour;
provide load flexibility
to bring significant lifestyle enhancements to remote areas in the developing
world;
provide reliability
necessary for effective operation over many years of household use; and,
maintain acceptability
in the areas of performance and safety.
Specifications – Topic (c) low-cost power for developing nations
|
Design Concept/Function |
Minimum
Target Requirement |
|
|
1. Manufacturing and operating cost |
Combined cost of manufacture, operation, maintenance, and
installation, amortized over ten year
life, not to exceed US$850. This
represents US$0.10 to $0.20 per kW-hr over the life of the system. It assumes high-volume production
(approximately 200 000 units/year). |
|
|
2. Complete package size and weight |
No special restrictions, except that the system must allow
assembly by a single individual with no special training and with hand tools. |
|
|
3. Input energy source |
Any “non-fuel” energy source, including photovoltaic, solar
thermal, wind generation, or water-driven generation. The widest possible application is of
interest. |
|
|
4. Output power capability |
Electrical output must provide a minimum of 100 W for at least 6
hrs per day, a minimum of 50 W for at least 12 hrs per day, and a minimum of
25 W for at least 18 hrs per day. |
|
|
5. Output specifications |
Teams may select any one of four output
configurations: 12 V dc (+-5%), 48 V
dc (+-5%), single-phase 120 V ac 60 Hz (voltage +-10%, frequency +-2%), or
single-phase 220 V ac 50 Hz (voltage +-10%, frequency +-2%), or the electric
utility configuration available in the team’s home country. Please choose only one, but it is required
that loads suitable for the chosen source be used. |
|
|
6. Energy storage |
There are no restrictions on the nature or type of any energy
storage elements used to meet the requirements. Possibilities include, but are not limited to, batteries, water
tanks, masses or springs, capacitors, thermal storage, or other means. Any energy storage used must be included
in the cost and reliability analysis. |
|
|
7. Weather |
The output energy requirements must be met during typical
weather conditions. The team may
select weather conditions at a typical site in their home country as the
basis for the design. Operation
during severe weather is not required.
Any weather-related de-rating must be described in the Final Report. |
|
|
8. Safety |
The system is intended for home use by untrained people, and
should be inherently safe. |
|
|
9. Loads |
Tests are based on a small refrigeration load, lighting loads
(such as compact fluorescent), and communications loads (TV/radio). Each team is encouraged to propose
additional loads that they believe will provide substantial life
enhancements, such as water pumps or purification systems, but must
demonstrate that the loads can be addressed within the available energy. Loads are not included in the cost or
reliability analysis. |
|
|
10. Load priority |
Loads must be provided with a priority setting that allows
automatic control of energy delivery where it is most needed. At least three loads should be supported
in this way. This can be provided
within the energy unit, for example, by providing three separate power
outlets, each with an internal priority setting. |
|
|
11. Protection |
Self-protection must be provided against short circuits or other
output faults. |
|
|
12. Environment |
Suitable for outdoor installation. Ambient temperature -20°C to +50°C. |
|
|
13. Lifetime |
The system should function for at least ten years with any
maintenance needs included in the cost analysis when subjected to normal use. |
|
|
14. Technical report |
Design, simulation, experimental results, lifetime analysis, and
cost study. The report must include
reliability and cost analysis to demonstrate that the design can meet the
ten-year lifetime requirement and the life-cycle cost objectives. |
|
|
Additional Hardware Specifications and Test
Considerations |
|
|
|
1. Safety |
The final rules will contain detailed safety information. No live electrical elements are to be
exposed when the system is fully configured. |
|
|
2. Storage temperature range |
-20 to 60°C |
|
|
3. Handling |
The unit must be robust enough for normal assembly and handling
by a technician with no special training. |
|
|
4. Shipping environment |
Can be shipped by conventional air freight or truck
freight. Multiple packages and
assembly in a kit form are permitted. |
|
|
5. Displays and data |
No displays or data capability are required, although some
general indication of the available power at any given moment is encouraged. |
|
|
13. Switch |
The unit must include an on/off switch. When the switch is off, no power is delivered
to any load. |
|
|
14. Inspections |
All prototypes of approved Finalist teams must pass safety
inspection prior to operation. All
prototypes must function correctly during a 15-minute initial operation check
before proceeding. |
|
|
15. Test energy sources |
An outdoor environment will be available for solar and wind
testing (mirrors will be used if necessary to produce insolation consistent
with tropical latitutes). A fan will
be available if needed to simulate normal winds, and a water source with a pressure
of 100 psi and a flow rate of up to 10 L/min will be available for testing of
water-powered units. |
|
|
16. Test duration |
An automated load sequencing operation will be tested for up to
24 hr continuous. The units will be
tested at power levels consistent with the “Output power capability”
specification above. |
|
|
17. Typical operation
tests |
Tests for steady-state performance, protection, interaction with
loads, and the priority system may be conducted. |
|
Additional Scoring
Teams are encouraged to
analyze the manufacture and utility of their design. Technical reports that include manufacturing plans based on
facilities in developing nations will receive extra merit during judging. Designs best suited for use in a wide range
of locations will also receive extra merit.
In the event that multiple teams are able to meet all the target
specifications, the designs with the best promise for wide application and
reports that address manufacturing plans in developing nations will be favored.
Specification Intent
The
specifications are intended to provide guidance rather than an exhaustive list
of requirements. All teams are
encouraged to develop novel solutions and test a wide range of ideas. The long-term purpose is to develop
cost-effective technologies that will bring major advances in energy sources
for homes in developing nations. Judges
will be encouraged to consider the spirit, innovation, and future promise of
each team’s work when reviewing entries.
Design Restrictions
In general, any
electrical, electronic, energy, mechanical, or other component may be used and
any technology is permitted. Keep in
mind the cost considerations and the intended safe use in domestic
applications. These factors will limit
the feasible range of component choices.
Funding Sources
IEEE provides
the Challenge Award.
IEEE and other
sponsors provide Program Awards.
Tentatively, DOD
will support the final testing events.
Individual
schools should solicit project funding from local or national sources. There is no limitation for the sources of
project funding.
Attachment 1
2003 Future Energy challenge Preliminary Team Information Form Topic – XXXX
Submit with
Proposal
Name of University:
DATE:
Corresponding Address (please include name):
TELPHONE:
FAX:
EMAIL:
Faculty Advisor(s):
Name Department E-Mail
_________________________
_________________________
____________________
_________________________
_________________________
____________________
_________________________
_________________________
____________________
PRELIMINARY Team Members:
Name Major
Field of Study
Degree and
Expected
Graduation Date
_______________________ ____________________________________
________________
_______________________ ____________________________________
________________
_______________________ ____________________________________
________________
_______________________ ____________________________________
________________
_______________________ ____________________________________
________________
_______________________ ____________________________________
________________
[The letter below is a typical sample, and should not
simply be copied. Please send a letter
with similar content on your University letterhead.]
Robert Myers
Administrative
Secretary
IEEE Power
Electronics Society
IEEE Industry
Applications Society
799 North
Beverly Glen
Los Angeles, CA
90077
Dear Mr. Myers,
Our university has organized a student team to participate in the 2003 Future Energy Challenge. Our proposal for the ( ) topic is enclosed. A Preliminary Team Participation Form is attached, listing our contact person, the faculty advisor(s), and some of the students who plan to be involved. The team will keep an eye on the Energy Challenge web site for detailed rules and other information. We understand that we will be notified whether we have been accepted to participate by August 1, 2002. If we are accepted, we agree to have our student team perform the design tasks and prepare the reports and hardware prototypes required for the competition. Our school is prepared to support the team with the following resources:
· A final year project course, XXX, has been authorized to provide engineering students across several disciplines with the opportunity to include this project in their curricula. Laboratory space has been arranged for this course.
· A faculty advisor, Prof. YYY, has been identified, and has been formally assigned to teach the project course and to advise the student team as a portion of her regular duties.
· A graduate student assistant has been identified to help manage the student team and to supervise direct laboratory activity. This student is supported with a Teaching Assistantship, which represents a funding commitment of our university of approximately ( ).
· The student team will be provided with an appropriate level of technician and machine shop support to assist them with package preparation and assembly. This assistance represents a funding commitment of approximately ( ), and we consider this as a matching commitment for any in-kind support received from external sponsors.
· In addition, we will provide limited funds to help secure special parts and equipment, with a total commitment of up to ( ).
· The student team will be encouraged to secure outside sponsorship. Our university strongly supports all these efforts, and will match any outside cash support 1:1 up to an additional total of ( ).
In the event that our school receives prizes from the competition, we are committed to using approximately ( )% of this money for scholarships for the student team members. The remainder of the funds will be added to our Team Design Program fund, which supports this and similar projects through sponsorship matching, travel funds for participation in competition events, and other direct costs of large team design projects. In the event that our team creates new inventions in the topic area, our university also provides the possibility of assisting with organization of a start-up company.
We understand the importance of student team projects in the engineering curriculum, and look forward to our participation in the 2003 Future Energy Challenge.
Sincerely,
(Head of Department, Dean of Engineering or similar school official)